Installation
Flaring Work
Main cause for gas leakage is due to defect of flaring work. Carry out correct flaring work in the following
procedure.
Cut the pipes and the cable.
1. Use the piping kit accessory or the pipes purchased
locally.
2. Measure the distance between the indoor and the
outdoor unit.
3. Cut the pipes a little longer than measured distance.
4. Cut the cable 1.5m(59.1 in) longer than the pipe
length.
Burrs removal
1. Completely remove all burrs from the cut cross
section of pipe/tube.
2. While removing burrs put the end of the copper
tube/pipe in a downward direction while removing
burrs location is also changed in order to avoid
dropping burrs into the tubing.
Putting nut on
• Remove flare nuts attached to indoor and outdoor
unit, then put them on pipe/tube having completed
burr removal.
(not possible to put them on after finishing flare
work)
Flaring work
1. Firmly hold copper pipe in a bar with the dimension shown in table below.
Outside diameter
mm
Ø6.35
Ø9.52
Ø12.7
Ø15.88
Ø19.05
2. Carry out flaring work with the flaring tool.
64
A
inch
mm
1/4
1.1~1.3
3/8
1.5~1.7
1/2
1.6~1.8
5/8
1.6~1.8
3/4
1.9~2.1
Inverter Single
Inverter Single
Inverter Single
Inverter Single
Copper
Slanted Uneven Rough
pipe
90
Point down
Flare nut
Copper tube
Bar
Bar
Copper pipe
Clamp handle
6RMI0-02A
Pipe
Reamer
Handle
Yoke
Cone
Red arrow mark