START-UP AND CHECK OUT

1. Turn the cuber's power switch to the clean (pump only) position. The water pump only should be op-
erational. Check for an even, steady flow of water over the evaporator top extrusion and down over
evaporator surface. Check that all ports of the water distribution tube are open for even water dis-
charge. The water pan should refill and the float should stop the incoming water supply.
2. Place the cuber's power switch in the on position. After a 2 second delay the compressor will start.
The condenser fan will operate when the condenser sensor signals the circuit board that its tempera-
ture is 100_F (38_C) The water pump will operate when the evaporator cools to 25_F (–3.9_C). De-
press the manual harvest switch located on the circuit board. The fan motor will stop and the water
dump valve will open. In 3 seconds the hot gas solenoid will open and 15 seconds after depressing
the manual harvest switch, the water pump will stop and the dump valve will close terminating the
dump cycle.
3. Hold the water curtain open for a maximum of 30 seconds; the product should shut down. Release
the water curtain(s). When the curtain(s) closes, there will be a 2 second delay, then the compressor
will start and the start–up process should begin for the next ice making mode.
4. If all product operation are as stated, allow product to operate and produce one slab of ice, then dis-
card the ice. Allow the product to continue operation to fill the storage bin.
FIGURE 4. SWITCH PANEL
5
POWER SWITCH