4.6 Powering off the Equipment
Procedure
Step 1 On the main menu, tap Shutdown.
Exercise cautions when performing operations on the equipment because the equipment is
under power.
Step 2 Switch off the front end circuit breaker and the main circuit breaker QF1.
Step 3 Install the air filters and the rear door.
----End
Issue 01 (2014-06-30)
You must switch off the front end circuit breaker when replace or maintain the air
conditioner components.
Only switch off the main circuit breaker QF1 when check whether the power-off function
is normal.