Maintenance; Equipment Start-Up Checklist - Zehnder Rittling SL Installation, Operation And Maintenance Manual

Table of Contents

Advertisement

Maintenance

Equipment start-up
checklist
16
Before each heating season,
remove front panel and inspect
coil fins for accumulation of dust
or other debris that may block
airflow between fins. Brush the
entire finned surface with a soft
bristled brush, brushing parallel
to the fins, taking care not to
damage the fins. Brushing should
be followed by cleaning with a
vacuum cleaner. Compressed
air can also be used by blowing
air through the coil fins, again
followed by vacuuming. If fins
are damaged during the cleaning
process, use an instrument
screwdriver or other small, flat-
edged tool to restraighten fins.
Receiving and inspection
Unit received undamaged
Unit received complete as
ordered
Unit structural support is
complete and correct
Handling and installation
Unit mounted level and square
Proper access is provided for
unit and accessories
Proper hot water line size to
unit
Unit protected from dirt and
foreign matter
For a deeper cleaning, spray
the finned surface with a mild
alkali cleaning solution and rinse
thoroughly.
Failure to maintain a clean coil
surface will result in reduced
performance.
Inspect for leaks. Replace front
cover. If a damper is included,
ensure that the damper is able to
move freely.
Heating connections
Connect field piping to unit
Pressure test all piping for
leaks
Install drain lines and traps, as
required
Insulate all piping, as required
Unit start-up
General visual inspection and
system inspection
Close all unit isolation valves
Flush water systems
After system has been flushed,
ensure all isolation valves are
open