4.2 Installation

J9
J3
P MAIN
P ITF
J9
J6
J4
J2 J1
Figure 4-1 Display unit, right side view
Cable assy.
ITF Board
J1
MAIN Board
10P6835
Connector Board Assy.
Cable Assy.
10S1901
1. Remove the display unit cover.
2. At the left side of the display unit, unfasten the
six screws fixing the MAIN Board (10P6835).
3. Fix the ITF Board to the MAIN Board with six
sets of spacers and spring washers (supplied) and
screws removed at step 2.
4. Connect cable assy. (supplied) between J9 on the
MAIN Board and J1 on the ITF Board (10P6840).
5. Remove dummy plate at rear of display unit and
install the connector board assy. there.
6. Connect the cables from the connector board assy.
to the ITF Board as follows:
Connector board assy.
NAV
CN-4A
CI
CN-5A
GYRO
CN-6A
LOG
CN-7A
7. Reattach the cover.