When installing two controller boards, install the controller boards in slots 2 and 3 of the 3-slot PCI riser
cage assembly installed in the primary PCIe riser location
93).

Installing the storage controller and FBWC module options

To install the component:
Power down the server (on page 20).
1.
Remove all power:
2.
Disconnect each power cord from the power source.
a.
Disconnect each power cord from the server.
b.
Do one of the following:
3.
Extend the server from the rack (on page 20).
o
Remove the server from the rack (on page 22).
o
Remove the access panel (on page 24).
4.
Remove the PCI riser cage
5.
If you intend to use an FBWC module, install the module on the storage controller. Depending on the
6.
controller model, the cable connector on the cache module might be facing up or down when the
module is installed on the controller board.
("Remove the PCI riser
cages" on page 26).
("PCI riser cage assembly
Hardware options installation 67