5.3 Connecting the Sensing Pipe

1 Remove the protection cap from the sensing pipe adaptor
on the burner mounting plate. Slacken the screw retaining
the sensing pipe 'P' clip (Fig. 13 & 15).
2. Manoeuvre the pipe so that the flared end aligns with the
adaptor. Engage the nut on the adaptor and tighten finger
tight. Tighten the 'P' clip retaining screw and tighten the nut
onto the adaptor using a suitable spanner (Fig. 14 & 15).
IMPORTANT: The sensing pipe must be connected to
enable the appliance to function safely and correctly.

5.4 Siting the Boiler

1. The fireplace and builders opening should be as
described under '4.0 Site Requirements' and be clean,
sound and level.
2. The flue should be installed as described under '4.0 Site
Requirements'.
3. It may be desirable to insert the required fittings into the
heat exchanger at this point, depending on the size of the
fireplace opening and whether or not the gravity injector tee
is to be used.
4. Locate the centre line of the finished opening and hearth
(Fig. 16).
5. Hold the boiler by its combustion box at either side of the
heat exchanger, lift from the packing base and place into the
opening.
6. Align the boiler centrally using the "V" mark on the front
centre of the appliance base. Check the distance between
each side of the base and opening. They should be equal
(Fig. 16).
7. The front edge of the base tray must align with the
finished front face of the wall or surround.
This is important for correct installation of the firefront.

5.5 Securing the Boiler

1. It is important that the boiler is secured to the base of the
builders opening.
2. Check the alignment within the opening is correct.
3. The hearth should be drilled as follows: Mark the hearth
through the two slots in the base. Remove the boiler and drill
the hearth. Insert the plugs supplied in the kit. Replace the
boiler. Secure the boiler with the two screws.