6.0 Installation
6.3
1. Remove the protection cap from the sensing
pipe adaptor on the burner mounting plate.
Slacken the screw retaining the sensing pipe 'P'
clip (Fig. 9b, 9c & 9d).
2. Manouevre the pipe so that the flared end
aligns with the adaptor. Engage the nut on the
adaptor and tighten finger tight. Tighten the 'P' clip
retaining screw and tighten the nut onto the
adaptor using a suitable spanner (Fig. 9c & 9d).
IMPORTANT: The sensing pipe must be
connected to enable the appliance to function
safely and correctly.
Fig. 9d
6.4
1. Stand the boiler upright on the carton base.
2. The hood may be fitted now or when the boiler
is in situ. Secure using the four nuts and set
screws provided (Fig. 10).
3. If a safety limit thermostat is required, it may be
convenient to fit it at this point of the installation.
6.5
1. The fireplace and builders opening should
be as described under '4.0 Site Requirements'
and be clean, sound and level.
2. The flue should be installed as described under
'4.0 Site Requirements'.
3. It may be desirable to insert the required fittings
into the heat exchanger at this point, depending
on the size of the fireplace opening and whether
or not the gravity injector tee is to be used.
4. Locate and mark the centre line of the finished
opening and hearth (Fig. 15).
Fig. 13
5. Hold the boiler by its combustion box at either
side of the heat exchanger, lift from the packing
base and place into the opening.
6. Align the boiler centrally using the "V" mark on
the front centre of the appliance base. Check the
distance between each side of the base and
opening. They should be equal (Fig. 15).
7. The front edge of the base tray must align with
the finished front face of the wall or surround.
This is important for correct installation of the
firefront.
8. Mark the hearth through the two slots in the
base (Fig. 14).
6.6
1. It is important that the boiler is secured to the
base of the builders opening.
2. The hearth should be drilled as follows:
X 2
Remove the boiler and drill the hearth. Insert
suitable plugs. Replace the boiler & check the
alignment within the opening is correct. Secure
the boiler with two screws.

Connecting the Sensing Pipe

Fitting the Boiler Hood

Siting the Boiler

Securing the Boiler

Advertisement

Table of Contents
loading

This manual is also suitable for:

44 075 03

Table of Contents