6. Commissioning
46
Baxi MainEco Combi and System 24 - 28 - 35 / 18 - 24
n Set the boiler to full load
1. Continue pressing for around 3 seconds on the B key. The status
signal for the B button is orange and always flashes green
briefly; Part load is set.
2. Press the B button again 2 times. The status signal for the B
button is orange and always goes off briefly 2 times; Full load is
set.
The full load status can only be reached via the part load
status.
3. Measure the percentage CO
removed).
Full load CO
2
n Set the boiler to part load
1. Continue pressing for around 3 seconds on the B key. The status
signal for the B button is orange and always flashes green
briefly; Part load is set.
2. Measure the percentage CO
removed).
Part load CO
WARNING
There MUST remain a "gap" between the full load and part
load values. The full load value must be 0.4% higher than
the part load value.
3. Briefly press the RESET button to return the boiler to normal
operating status.
in the flue gases (Front panel
2
must be between 9.15 and 9.50 %.
in the flue gases (Front panel
2
must be between 8.70 and 9.05 %.
2
02092014 - 7619497-02