Working clearances

For access to the appliance, it is recommended that the following clearances
are observed (see figure):
AA: around the appliance's control column and cleaning openings: 100 cm.
BB: all sides of the appliance: 50 cm.
Above the appliance (room to replace the anodes):
-
100 cm if using fixed anodes, or
-
50 cm if using flexible anodes.
If the available clearance is less than 100 cm, flexible magnesium anodes
may be ordered.
Note
When installing the appliance, be aware that any leakage from the tank
and/or connections can cause damage to the immediate environment or floors
below the level of the boiler room. If this is the case, the appliance should be
installed above a wastewater drain or in a suitable metal leak tray.
The leak tray must have an appropriate wastewater drain and must be at least
5cm deep with a length and width at least 5cm greater than the diameter of the
appliance.
Working clearances
IMD-0262 R2