Installing Vent Pipe (DVP and SLP Pipe)

A. Assemble Vent Sections (DVP Pipe Only)
Attach Vent to the Firebox Assembly
Note: The end of the pipe sections with the lanced tabs will face
toward the appliance.
Attach the fi rst pipe section to the starting collar:
• Lanced pipe end to the starting collar
• Inner pipe over inner collar
• Push the pipe section until all lanced tabs snap in place
• Lightly tug on pipe to confi rm it has locked.
Commercial, Multi-family (Multi-level exceeding two sto-
ries), or High-Rise Applications
All outer pipe joints must be sealed with high temperature
silicone, including the slip section that connects directly to
the horizontal termination cap.
• Apply a bead of silicone sealant inside the female outer
pipe joint prior to joining sections. See Figure 8.1
• Only outer pipes need to be sealed. All unit collar, pipe,
slip section, elbow and cap outer fl ues shall be sealed
in this manner, unless otherwise stated.
WARNING! Risk of Fire or Explosion! DO NOT break
silicone seals on slip sections. Use care when remov-
ing termination cap from slip pipe. If slip section seals
are broken during removal of the termination cap, vent
may leak.
Assemble Pipe Sections (DVP Pipe Only)
Per Figure 8.2:
• Start the inner pipe on the lanced end of section A into
the fl ared end of section B.
• Start the outer pipe of section A over the outer pipe of
section B.
• Once both vents sections are started, push fi rmly until
all lanced tabs lock into place.
• Lightly tug on the pipe to confi rm the tabs have locked.
It is acceptable to use screws no longer than 1/2 in. (13
mm) to hold outer pipe sections together. If predrilling holes,
DO NOT penetrate inner pipe.
For 90° and 45° elbows that are changing the vent direction
from horizontal to vertical, one screw minimum should be
put in the outer fl ue at the horizontal elbow joint to prevent
the elbow from rotating. Use screws no longer than 1/2 in.
(13 mm). If predrilling screw holes, DO NOT penetrate
inner pipe.
34
Heat & Glo • SL-550 / 750 / 950TR-E • 2118-900 Rev. K • 9/08
Figure 8.1 High Temperature Silicone Sealant
A
B
Figure 8.2
Note:
Make sure that the seams are not aligned to prevent
unintentional disconnection.
CORRECT
INCORRECT
Figure 8.4 Seams