Toshiba G9000 SERIES Installation And Operation Manual page 82

480/480 v 80/100/160/225/300/500/750 kva
Hide thumbs Also See for G9000 SERIES:
Table of Contents

Advertisement

C)
Bypass Operation Procedure
** Transfer from Inverter to Bypass
1. Check for "SYNC" on the LCD.
2. Press the "START/STOP" icon on the LCD.
3. Follow the "SHUTDOWN GUIDANCE" and Press the "STOP" icon on the LCD.
** Transfer from bypass to inverter.
UPS
1. Press the "START/STOP" icon on the LCD.
2. Follow the "STARTUP GUIDANCE" and Press the "START" icon on the LCD..
!
NOTE
72
When "REMOTE OPERATION MODE" is displayed on the LCD panel, the inverter
start operation can only be performed remotely. If local inverter start or stop operation is
required (at the UPS), select "LOCAL ONLY" or "REMOTE & LOCAL" in the
OPERATION MENU.