6. Remove 1 E-ring and 1 screw (CBS, 3x6, F/Zn) securing the right parallelism adjustment
bushing to the top frame. Then turn the bushing forward until it fits into the cutout in the top
frame and slide it to the right. (Refer to Figure 3-46.)
Figure 3-46. Parallelism Adjustment Bushing Removal
7. Remove the compression spring (19.9 g) using tweezers. Then shift the sub pulley holder to
the right and remove it from the top frame. (Refer to Figure 3-47.)
Rev. A
Figure 3-47. Sub Pulley Holder Removal
Disassembly and Assembly