Installing System Hardware
Measuring with the Rack Template
Telco Rack Configurations
If you are installing components in a telco rack, refer to the telco rack template and
documentation that ship with the telco enclosure option kits.
Power Bus Box Configurations
If you are installing a power bus box configuration, refer to the power bus box rack
template and documentation that ship with the power bus box option kit.
Scalable and Mini Bus Bar Configurations
If you are installing a scalable or mini bus bar configuration, refer to the template and
documentation that ship with either option kit.
Installing the Rack Rails and Cage Nuts
You must install two rack rails to support each enclosure. Rack rails have the
following features:
•
Adjustable depth of 60.96 cm to 91.44 cm (24 inches to 36 inches)
IMPORTANT: For proper bus bar installation and clearance, the rack rail depth must be
set from 73.66 cm to 76.20 cm (29 inches to 30 inches).
•
Depth indicator, visible in the middle of the rail
•
"L" and "R" markings to identify left and right rack rails (from the front of the
rack)
WARNING: To reduce the risk of personal injury and damage to the
equipment, always begin by mounting the heaviest item on the bottom of the
rack. Continue to populate the rack from the bottom to the top. Failure to do so
may make the rack unstable.
3-2
HP ProLiant BL p-Class System Setup and Installation Guide