Check The Installation; Connect To Power And Check The Leds - NETGEAR GSM7352SNA - Prosafe 48 Port Gigabit L3 Managed Stackable Switch Installation Manual

Managed stackable layer 3 switches
Table of Contents

Advertisement

Managed Stackable Layer 3 Switches GSM7328S, GSM7352S and GSM7328FS Hardware Instal-
4. Align the bracket and rack holes. Use two pan-head screws with nylon
washers to fasten each bracket to the rack.
5. Tighten the screws with a No. 2 Phillips screwdriver to secure the switch in
the rack.

Check the Installation

Before you apply power, perform the following checks:
1. Inspect the equipment thoroughly.
2. Verify that all cables are installed correctly.
3. Check cable routing to ensure that cables are not damaged and will not create
a safety hazard.
4. Be sure that all equipment is mounted properly and securely.

Connect to Power and Check the LEDs

The switch does not have an ON/OFF switch. The only way to apply or remove
power is to connect or disconnect the power cord. Before you connect the power
cord, select an AC outlet that is not controlled by a wall switch (which can turn off
power to the switch).
After you select an appropriate outlet, follow these steps to apply AC power.
1. Connect one end of the AC power adapter cable to the rear of the switch, and
the other end to a grounded 3-pronged AC outlet.
2. Check the Power LED on the front panel of the switch. The LED should light
up in the following sequence:
If the Power LED does not light up, check that the power cable is plugged in
correctly and that the power source is good. For help with troubleshooting,
see Chapter 4, "Troubleshooting".
3-6
The LED turns yellow as the switch runs a Power-On Self-Test (POST).
If the switch passes the test, the LED turns green. The switch is working
and ready to pass data.
If the POST fails, the Power LED blinks yellow.
v1.0, February 2007
Hardware Installation

Advertisement

Table of Contents
loading

Table of Contents