7 - WATER CONNECTIONS

ATTENTION: Before carrying out any water connections
install the water box purge plugs (one plug per water box in
the lower section supplied in the control box).
For size and position of the heat exchanger water inlet and outlet
connections refer to the certified dimensional drawings supplied 
with the unit.
The water pipes must not transmit any radial or axial force to the
heat exchangers nor any vibration.
The  water  supply  must  be  analysed  and  appropriate  filtering, 
treatment, control devices, isolation and bleed valves and circuits
built in, to prevent corrosion, fouling and deterioration of the pump
fittings. Consult either a water treatment specialist or appropriate 
literature on the subject.

7.1 - Operating precautions

The water circuit should be designed to have the least number of
elbows and horizontal pipe runs at different levels. Below the main 
points to be checked for the connection:
• Comply with the water inlet and outlet connections shown
on the unit.
• Install manual or automatic air purge valves at all high points
in the circuit(s).
• Use a pressure reducer to maintain pressure in the circuit(s)
and install a relief valve as well as an expansion tank.
• Install thermometers in both the entering and leaving water
connections.
• Install drain connections at all low points to allow the whole
circuit to be drained.
• Install stop valves, close to the entering and leaving water
connections.
• Use flexible connections to reduce the transmission
of vibrations.
• Insulate all pipework, after testing for leaks, both to reduce
heat gains and to prevent condensation.
• Cover the insulation with a vapour barrier.
Where  there  are  particles  in  the  fluid  that  could  foul  the  heat 
exchanger, a screen filter should be installed ahead of the pump, 
or directly at the exchanger inlet in case the pump is more than
20m away. The mesh size of the filter must be 1.2 mm.
Before the system start-up verify that the water circuits are
connected to the appropriate heat exchangers (e.g. no reversal
between evaporator and condenser). Do not introduce any
significant static or dynamic pressure into the heat exchange circuit 
(with regard to the design operating pressures). Before any start-
up  verify  that  the  heat  exchange  fluid  is  compatible  with  the 
materials and the water circuit coating. The use of different metals 
on hydraulic piping could generate eletrolytic pairs and
consequently  corrosion.  It  could  be  needed  to  add  sacrificial 
anodes. In case additives or other fluids than those recommended 
by Carrier are used, ensure that the fluids are not considered as 
a  gas,  and  that  they  belong  to  class  2,  as  defined  in  directive 
2014/68/EU.
20
Carrier recommendations on heat exchange fluids:
• No NH
4+
ammonium ions in the water, they are very
detrimental for copper. This is one of the most important
factors for the operating life of copper piping. A content of
several tenths of mg/l will badly corrode the copper over
time.
• Cl- Chloride ions are detrimental for copper with a risk of
perforations by corrosion by puncture. If possible keep
below 125 mg/l.
• SO
2-
sulphate ions can cause perforating corrosion, if their
4
content is above 30 mg/l.
• No fluoride ions (<0,1 mg/l).
• No Fe
2+
and Fe
3+
ions with non negligible levels of dissolved
oxygen must be present. Dissolved iron < 5 mg/l with
dissolved oxygen < 5 mg/l.
• Dissolved silica: silica is an acid element of water and can
also lead to corrosion risks. Content < 1 mg/l.
• Water hardness: > 0,5 mmol/l. Values between 1 and 2,5
can be recommended. This will facilitate scale deposit that
can limit corrosion of copper. Values that are too high can
cause piping blockage over time. A total alkalimetric titre
(TAC) below 100 mg/l is desirable.
• Dissolved oxygen: Any sudden change in water oxygenation
conditions must be avoided. It is as detrimental to
deoxygenate the water by mixing it with inert gas as it is to
over-oxygenate it by mixing it with pure oxygen. The
disturbance of the oxygenation conditions encourages
destabilisation of copper hydroxides and enlargement of
particles.
• Electric conductivity 10-600µS/cm.
• pH: Ideal case pH neutral at 20-25°C 7 < pH < 8
When the water circuit must be emptied for longer than one month
or immediately if the water does not comply with the above
description, the circuit must be either totally dried or placed under
0.5 bar maximum nitrogen charge. This is done to avoid any
damage of the exchanger copper tubes with corrosion by
differential aeration. In case of nitrogen charge, the circuit must 
be equipped with relief valves to avoid overpressure due to
refrigerant leakage. Charging and removing heat exchange fluids 
should be done with devices that must be included on the water
circuit by the installer. Never use the unit heat exchangers to add
heat exchange fluid.
CAUTION: Filling, completing and draining the water circuit
charge must be done by qualified personnel, using the air
purges and materials that are suitable for the products.
Charging and removing heat exchange fluids should be done
with devices that must be included on the water circuit by the
installer. Never use the unit heat exchangers to add heat
exchange fluid.