1.2.3 Air Tight Test and Vacuum Drying
Note:
1.2.3.1
Preparations
<Needed tools>
Gauge manifold
Charge hose valve
Vacuum pump
<The system for air tight test and vacuum drying>
Air tight test, Vacuum drying
(Close valve A and shutoff valves certainly. Otherwise the
refrigerant in the unit are released.)
Note:
Test Operation
Always use nitrogen gas for the airtightness test.
Absolutely do not open the shutoff valve until the main power ciruit insulation measurement
has been completed. (measuring after the shutoff valve is opened will cause the insulation
value to drop.)
• To prevent entry of any impurities and insure sufficient
pressure resistance, always use the special tools
dedicated for R-410A.
• Use charge hose that have pushing stick for connecting
to service port of shutoff valves or refrigerant charge
port.
• The vacuum pump for vacuum drying should be able to
lower the pressure to –100.7kPa
(5 Torr –755mm Hg).
• Take care the pump oil never flow backward into the
refrigerant pipe during the pump stops.
Referring to figure 28, connect an nitrogen tank, refrigerant tank, and a vacuum pump to the
outdoor unit.
The shutoff valve and valve A~C in figure 28 should be open or closed as shown in the table
below.
Gouge manifold
R-410A cylinder
(with siphon)
of valve A, B and C and shutoff valves
The airtightness test and vacuum drying should be done using the liquid
side and gas side shutoff valve service ports.
See the [R-410A] Label attached to the front plate of the outdoor unit for
details on the location of the service port (see figure at right).
See [Shutoff valve operation procedure] for details on handling the
shutoff valve. (Refer page 149)
The refrigerant charge port is connected to unit pipe.
When shipped, the unit contains refrigerant, so use caution when
attaching the charge hose.
Liquid side
shutoff valve
Gas side
shutoff valve
Charge
Shutoff valve
hose
service port
Valve B
Valve C
Vacuum pump
Valve A
fig. 28
Valve
A
B
Close Open Open
Test Operation
Refrigerant charge port
Outdoor
Outdoor
unit
unit
To indoor unit
Interunit pipings
Gas flow
shutoff valve
C
Liquid side
Gas side
Close
Close