Figure 6-3 Manifold Gauge Set; Figure 6-4 R-134A Manifold Gauge/Hose Set - Carrier 69NT20-551-300 TO 399 Operation And Service

Container refrigeration units
Table of Contents

Advertisement

A R-134a manifold gauge/hose set with self-sealing
hoses (see Figure 6-4) is required for service of the
models covered within this manual. The manifold
gauge/hose set is available from Carrier Transicold.
(Carrier Transicold P/N 07-00294-00, which includes
items 1 through 6, Figure 6-4.) To perform service using
the manifold gage/hose set, do the following:
a. Preparing Manifold Gauge/Hose Set For Use
1. If the manifold gauge/hose set is new or was
exposed to the atmosphere it will need to be eva-
cuated to remove contaminants and air as follows:
2. Back seat (turn counterclockwise )both field service
couplings (see Figure 6-4) and midseat both hand
valves.
3. Connect the yellow hose to a vacuum pump and re-
frigerant 134a cylinder.
SUCTION
PRESSURE
GAUGE
OPENED
(Backseated )
HAND VALVE
To Low Side
Access Valve
3
BLUE
4
6
Blue Knob
1. Manifold Gauge Set
2. Hose Fitting (0.5-16 Acme)
3. Refrigeration and/or Evacuation Hose
.
(SAE J2196/R-134a)
4. Hose Fitting w/O-ring (M14 x 1.5)
5. High Side Field Service Coupling
6. Low Side Field Service Coupling

Figure 6-4 R-134a Manifold Gauge/Hose Set

7. Evacuate to 10 inches of vacuum and then charge
with R-134a to a slightly positive pressure of 0.1 kg/
cm@ (1.0 psig).
8. Front seat both manifold gauge set valves and dis-
connect from cylinder. The gauge set is now ready
for use.
b. Connecting Manifold Gauge/Hose Set
To connect the manifold gauge/hose set for reading
pressures, do the following:
1. Remove service valve stem cap and check to make
sure it is backseated. Remove access valve cap.
(See Figure 6-1)
2. Connect the field service coupling (see Figure 6-4)
to the access valve.
3. Turn the field service coupling knob clockwise, which
will open the system to the gauge set.
T-322
DISCHARGE
1
PRESSURE
GAUGE
CLOSED
(Frontseated)
HAND VALVE
To High Side
Access Valve
2
3
RED
3
YELLOW
5
4
Red Knob
2
4. To read system pressures: slightly midseat the ser-
vice valve.
5. Repeat the procedure to connect the other side of
the gauge set.
To prevent trapping liquid refrigerant in the
manifold gauge set be sure set is brought to
suction pressure before disconnecting.
c. Removing the Manifold Gauge Set
1. While the compressor is still ON, backseat the high
side service valve.
2. Midseat both hand valves on the manifold gauge set
and allow the pressure in the manifold gauge set to
be drawn down to low side pressure. This returns
any liquid that may be in the high side hose to the
system.
3. Backseat the low side service valve. Backseat both
field service couplings and frontseat both manifold
set valves. Remove the couplings from the access
valves.
4. Install both service valve stem caps and service port
caps (finger-tight only).
6.4 PUMPING THE UNIT DOWN
To service the filter-drier, economizer, expansion
valves, moisture-liquid indicator, suction modulation
valve, economizer solenoid valve, unloader solenoid
valve or evaporator coil, pump the refrigerant into the
high side as follows:
The scroll compressor achieves low suc-
tion pressure very quickly. Do not operate
the compressor in a deep vacuum, internal
damage will result.
a. Attach manifold gauge set to the compressor suction
and discharge service valves. Refer to paragraph 6.3.
b. Start the unit and run in the frozen mode (controller
set below --10°C) for 10 to 15 minutes.
c. Check function code Cd21 (refer to paragraph 3.2.2).
The economizer solenoid valve should be open. If
not, continue to run until the valve opens.
d. Frontseat the oil return service valve then, frontseat
the liquid line service valve. Place start-stop switch in
the OFF position when the suction reaches a positive
pressure of 0.1 kg/cm@ (1.0 psig).
e. Frontseat the economizer service valve and then
frontseat the suction and discharge service valves.
The refrigerant will be trapped between the compres-
sor suction service valve and the liquid line valve.
f. Before opening up any part of the system, a slight
positive pressure should be indicated on the pressure
gauge. If a vacuum is indicated, emit refrigerant by
cracking the liquid line valve momentarily to build up a
slight positive pressure.
g. When opening up the refrigerant system, certain
parts may frost. Allow the part to warm to ambient
6-2
CAUTION
CAUTION