Preparations For A Qimarox Installation (Optional) - Qimarox PD2 User Manual

Pallet dispenser
Table of Contents

Advertisement

and the bolts of the supports are fastened
properly before removing the hoisting belt or
the hoisting chain.
6. Mount covers back on machine.

5.5 Preparations for a Qimarox installation (optional)

The preparations given below will need to be done before Qimarox can assemble the
machine on site. All equipment listed below must be present before and during
assembly.
1. Indicate the contact person to whom the mechanic of Qimarox must report when
arriving or leaving before and after the installation.
2. Make sure that the mechanic of Qimarox is assisted by qualified mechanics of the
client. Refer to chapter 3.
3. Make sure that the place where the assembly takes place:
-
is accessible, has sufficient light and is at room temperature.
-
has been laid out such that the mechanics can work safely and without
interruptions.
-
is suitable for drilling and/or grinding, if necessary.
4. Provide hoisting equipment:
-
preferably a bridge crane, minimum carrying capacity 1.5 x the weight of the
machine.
-
or a fork-lift truck combined with a hoist with a minimum capacity of 2 x the
weight of the machine at a lifting height with a minimum height of the machine
plus 2 meters.
5. Provide electric power (230 V AC) at a maximum of 5 metres from the place of
assembly of the machine.
6. Provide the correct safety provisions:
-
Moveable scaffolding or an aerial work platform.
-
Personal protection equipment.
UM Pallet dispenser PD2 v2.0 EN
CAUTION
Make sure that the machine stays in balance!
Installation
31