18
|
Commissioning
18.3 Checklist during commissioning
18.3.1 About the test run
Installer and user reference guide
98
Air inlet/outlet
Check that the air inlet and outlet of the unit is NOT obstructed by paper sheets,
cardboard, or any other material.
Fuses, circuit breakers, or protection devices
Check that the fuses, circuit breakers, or the locally installed protection devices are of the
size and type specified in the chapter
a fuse nor a protection device has been bypassed.
Field wiring
Be sure that the field wiring has been carried out according to the instructions described in
"15 Electrical
installation" [
applicable legislation.
Installation date and field setting
Be sure to keep a record of the installation date on the sticker on the rear of the front
panel according to EN60335‑2‑80 and keep record of the contents of the field setting(s).
EKVDX
In case an EKVDX is installed, also see chapter Commissioning in the EKVDX installation and
operation manual.
To perform a test run.
After completing the installation of the system, turn on the power of the heat
reclaim ventilation units. Refer to the manual of the controller of each unit
(controller for air conditioner, central controller, etc.) to conduct a trial operation.
"15 Electrical
installation" [
4
50], according to the wiring diagrams and according to the
4
50]. Be sure that neither
VAM350~2000J8VEB
Heat reclaim ventilation unit
4P664012-1 – 2021.08