Sintesis™ RTAF
Installation Completion Check Sheet and Request for Trane Service
Important:
A copy of this completed form must be submitted to the Trane service agency that will be responsible for the start-
up of the chiller. Start-up will NOT proceed unless applicable items listed in this form have been satisfactorily
completed. See unit IOM RTAF-SVX001*-EN for detailed installation instructions.
To:
S.O. Number:
Job/Project Name:
Address:
The following items are being installed and will be completed by:
Important:
Start-up must be performed by Trane or an agent of Trane specifically authorized to perform start-up of Trane
products. Contractor shall provide Trane (or an agent of Trane specifically authorized to perform start-up) with
notice of the scheduled start-up at least two weeks prior to the scheduled start-up.
Important:
It is required that heaters are energized for a minimum of 24 hours prior to start up. Therefore, chiller
should have power for this amount of time before Trane Service arrives to do start-up.
Copyright
This document and the information in it are the property of Trane, and may not be used or
reproduced in whole or in part without written permission. Trane reserves the right to revise this
publication at any time, and to make changes to its content without obligation to notify any person
of such revision or change.
Trademarks
All trademarks referenced in this document are the trademarks of their respective owners.
Revision History
.
Check boxes if the task is complete or if the answer is "yes."
1. Chiller
 Installation meets foundation requirements.
 In place and piped.
 Isolation pads or elastomeric pads installed (optional).
2. Refrigerant Pressure Check
 PRIOR to water being added to the system, use gauges to verify positive pressure in the evaporator and condenser.
Lack of pressure could indicate a system leak. When charging in the factory, approximately 95% of the refrigerant
charge is isolated in the evaporator, and the other 5% is contained in the condenser and compressor. In the event that
no pressure is present, contact local Trane service.
Note: Verification must be done by gauges. Do NOT rely only on values from unit transducers.
3. Piping
 Water piping flushed before making final connections to the system
Chilled water piping connected to:
 Evaporator
 Air handling units
 Pumps
 Flow switch or flow proving device installed
 Strainer installed in entering evaporator water piping and cleaned
 Drain and vents in both evaporator waterboxes are piped with shutoff valve, or plugs have been reinstalled.
 Water supply connected to filling system
 Does unit have freeze inhibitor? If unit has freeze inhibitor:
 Verify type and concentration correct per unit submittal
RTAF-ADF001D-EN
Added drain/vent requirement in Piping.
Added NEC reference to Wiring