Verify line voltage and power cord.

WA RNING

Power consumption

Table 1
GC power requirements
*
Line voltage
120 single phase*(–10% / +10%)
200–240 V single/split phase,
+10 to –10%
* Users of 100 V power (Japan) receive the 120 V US power option with a 100 V/120 V step up transformer.

Power cords available

Agilent Intuvo 9000 GC Installation
1
Verify that the power cord is correct for the voltage and
location. See
"Power cords available"
The power cord termination is determined by the country
where the GC is ordered.
Electrical shock hazard. To avoid injury, only a qualified person
should measure line voltage.
2
Have a qualified person measure the actual power outlet
voltage and verify it meets the tolerance requirements listed
in
Table 1
on page 15. See also
The next sections detail the power specifications and
requirements for reference.
The number and type of electrical outlets required for
installation depends on the size and complexity of your system.
A GC system with a computer, monitor, printer, and hub
requires five outlets. The GC does not require a dedicated
ground, but since the GC can draw up to 12 A maximum,
depending on the line voltage, you may not want other
devices on the same circuit.
Frequency
Current
50/60
12 A
(–5% / +5%)
50/60
7.7 / 6.5
(–5% / +5%)
Power line conditioners should not be used with the GC.
Table 2
lists the power cords available for the GC. If your power
cord is incorrect, order the cord appropriate for the country.
on page 15.
"Grounding"
Maximum continuous
power consumption (VA)
1296
1548
1
Installing the GC
on page 18.
Power outlet current
rating
15 A
10 A
15