Connection and commissioning

5.4 Switching on and testing

5.4
Switching on and testing
Procedure for switching on and checking the charging station.
Perform the following steps to switch on the charging station.
1. Switch the power supply on.
Switch on the backup fuses, the load breaker switch and the RCCB.
2. Test run and approval:
Carry out measurements according to the German occupational accident insurance
association (DGUV) regulation 3, or according to the comparable regional regulations.
5.5

Commissioning

Procedure for setting up the charging station
Note
Option: Configuration and communication test
If you have selected the option for customer-specific configuration including SIM card and
communication test to the backend, these settings have already been made at the factory.
Starting commissioning:
1. System configuration:
A Web interface is available to you for system configuration. To do this, connect a laptop to
the LAN interface using an RJ45 cable (Charging controller (Page 23)).
Make sure that the network settings of the LAN interface on your laptop are set to DHCP.
Open a web browser. Enter the URL specified below in the address line of the browser.
2. Log in with the admin user and the system password.
3. Adjust the parameters according to the specifications of your provider and backend
operator.
URL
http://192.168.32.1
The serial number of the system can be found on the rating plate (Page 18).
44
User
admin
Operating Instructions, 07/2020, A5E48573001-AB