4. Piping Length & Height

Synchro Operation

Install the branch pipe so that pipe length and difference between high and low will not exceed below Spec.
Pipe Length & Height
Total(L1+L2+L3+L4+L5)
Main Pipe(L1)
Branch Pipe (L2+L3+L4+L5)
Each
Indoor-Outdoor (H1)
Indoor-Indoor (H2)
L6
When installing the branch pipe, direction and angle of installation is not limited.
Take care so that burrs and foreign material may not enter into the cutting surface when connecting.
Connect remaining those by cutting or direct insertion to the diameter of pipe.
L2
Indoor Unit
L3
L4
Indoor Unit
L5
L6
Branch
L1
Notes
L1 (m)
L2~L5 (m) : Branch Piping Length (Branching Kit ~ Indoor Unit)
L6 (m)
H1 (m)
H2 (m)
Refer to the specifications of Outdoor Unit for Maximum limit.
Indoor Unit
Indoor Unit
: Main Piping Length (Outdoor Unit ~ Branching Kit)
: Length Difference (the Nearest Indoor Unit ~ the farthest Indoor Unit)
: Height Difference (Outdoor Unit ~ Indoor Unit)
: Height Difference (Indoor Unit ~ Indoor Unit)
Spec(MAX.)
Standard Inverter - Synchro
[Unit : m]
80
45
40
15
30
1
10
7