Figure 6-1: Installation Procedure For Slave Ups (1); Figure 6-2: Installation Procedure For Slave Ups (2) - Toshiba G2020 Series Installation Manual

Sync kit 480/480 v 500/750 kva
Hide thumbs Also See for G2020 Series:
Table of Contents

Advertisement

Part No. 3
Three (3) Fuses
Part No. 2
Fuse holder
* Use part No.14
Two (2) screws (M4) with
spring washer and flat washer
for the Fuse holder
* Use part No.16, No.17
Four (4) spring washers
Four (4) flat washers
From
MASTER UPS
Part No. 1
VS1 PCB (VSAU-16*)
* Use part No.13
Four (4) screws (M3)
with spring washer
and flat washer
for VS1 PCB.
Part No. 8,9,10
Wires
UN - V
VN - W
WN - U
10
Part No. 12
Four (4) Spacers

Figure 6-1: Installation procedure for SLAVE UPS (1)

A
B
C

Figure 6-2: Installation procedure for SLAVE UPS (2)

Part No. 18
Fuse label
U
Part No. 5
V
Wire (3-twisted)
U - U
W
V - V
W - W
CN1
To UP1 PCB
(Main control board)
Part No. 10
Wire
* Use part No.14
One (1) screw (M4) with
spring washer and flat washer
for grounding.
G2020 TOSHIBA SYNC KIT Installation Manual - 200153-001