Cabling
A cable junction is required
between the indoor and
outdoor area
see Figure 12-2
Figure 12-2
Fiber-optic cables, installation using distribution boxes
CPU 410-5H Process Automation/CPU 410 SMART
System Manual, 10/2013, A5E32631667-AA
Components required
One distribution/junction box
•
per branch
Installation and patch cables are
connected via the distribution box.
Either ST or SC plug-in
connections can be used, for
example
Check the cross-over installation
when you wire the CPUs.
12.3 Selecting fiber-optic cables
Specification
Connector type ST or SC, for example, to match
•
other components
Synchronization modules
191