Installation Of Vibration Isolators; Installation; Shipping Braces; Pipework Connection - York eco YCAS Series Manual

Optimized r-407c air-cooled liquid chiller
Table of Contents

Advertisement

Installation

The clearance dimensions given are
necessary to maintain good airflow
and ensure correct unit operation. It
is also necessary to consider access re-
quirements for safe operation and
maintenance of the unit and power
and control panels. Local health and
safety regulations, or practical consid-
erations for service replacement of
large components, may require larger
clearances than those given in the
Technical Data Section.

INSTALLATION OF VIBRATION ISOLATORS

Installation
A more detailed installation instruc-
tion is provided on page 156.
32

SHIPPING BRACES

PIPEWORK CONNECTION

General Requirements

The maximum flow rate and pressure
drop for the cooler must not be ex-
ceeded at any time. Refer to the Tech-
nical Data Section for details.
The liquid must enter the cooler by the
inlet connection. The inlet connection
for the cooler is at the far end of the
unit when viewed from the power and
control panels.
A flow switch must be installed in the customer
pipework at the outlet of the cooler and wired back
to the control panel using shielded cable.