Converting the gas type (only for operation with LPG)
1. To change the gas type on the control unit, see
"Commissioning the system with the commission-
ing assistant"
Note
Mechanical conversion on the gas train is not pos-
sible.
Checking the static pressure and supply pressure
C
A
Fig. 29
Cover panel
A
Test connector
B
Type plate
C
Danger
CO formation as a result of incorrect burner
adjustment can have serious health implications.
Carry out a CO test before and after work on
gas appliances.
Operation with LPG
Purge the LPG tank twice on commissioning/replace-
ment. Vent the tank and gas connection line thoroughly
after purging.
01. Close the gas shut-off valve.
02. Undo clips and remove cover panel
03. Undo screw in test connector
but do not remove it. Connect the pressure gauge.
04. Open the gas shut-off valve.
2. Affix label "G31" (supplied with the technical docu-
B
05. Test the static pressure and record it in the report.
06. Start the boiler.
07. Check the supply (flow) pressure. For set values,
A
.
on the gas train,
B
Commissioning, inspection, maintenance
mentation) adjacent to the type plate on the out-
side of the appliance.
Set value: Max. 57.5 mbar (5.75 kPa).
Note
During commissioning, the appliance can enter a
fault state if there are airlocks in the gas line.
Reset the appliance after approx. 5 s (see operat-
ing instructions).
see the following table.
Note
Use a suitable measuring device with a resolution
of at least 0.1 mbar (0.01 kPa) to check the supply
pressure.
35