Start-Up; Pre Start-Up - Raypak XTherm Series Installation & Operating Instructions Manual

Table of Contents

Advertisement

START-UP

NOTE: The following steps must be performed by a
factory-trained technician.

Pre Start-up

Filling System (Heating Boilers)
Fill system with water. Purge all air from the system.
Lower system pressure. Open valves for normal sys-
tem operation, and fill system through feed pressure.
Manually open air vent on the compression tank until
water appears, then close vent.
Air Purge
Purge all air from system before heater operation. This
can be normally accomplished by opening a down-
stream valve.
The XTherm 2505-4005 models have two air vent
valves located on top of the upper headers as stan-
dard. These valves are used to purge air from the
heat exchanger.
CAUTION: An air vent valve should be installed at
the highest point in the system for proper operation.
If water piping is located higher than the header, an
air vent valve should be located at the highest point
in the installed system.
Venting System Inspection
1. Check all vent pipe connections and flue pipe
ma-terial.
2. Make sure vent terminations are installed per code
and are clear of all debris or blockage.
For Your Safety
This appliance has a hot surface igniter. It is equipped
with an ignition device which automatically lights the
burners. Do not try to light the burners by hand.
WARNING: If you do not follow these instructions
exactly, a fire or explosion may result causing
property damage, personal injury or loss of life.
BEFORE OPERATING, smell all around the appliance
area for gas. Be sure to smell near the floor because
some gas is heavier than air and will settle on the floor.
WHAT TO DO IF YOU SMELL GAS:
Do not try to light any appliance.
Do not touch any electrical switch; do not use any
telephone in your building.
Immediately call your gas supplier from a neigh-
bor's telephone. Follow the gas supplier's
instructions.
If you cannot reach your gas supplier, call the fire
department.
Use only your hand to turn the gas control valve
handle. Never use tools. If the handle will not turn
by hand, do not try to repair it; call a qualified ser-
vice technician. Forced or attempted repair may
result in a fire or explosion.
Do not use this appliance if any part has been
under water, immediately call a qualified service
technician to inspect the appliance and to replace
any part of the control system and any gas control
which has been under water.
Check around unit for debris and remove combus-
tible products, i.e. gasoline, etc.
Pre Start-up Check
1. Verify the heater is filled with water.
2. Check system piping for leaks. If found, repair
immediately.
3. Vent air from system. Air in system can interfere
with water circulation.
4. Purge air from gas line to heater.
Initial Start-up
Required tools
(1) 12-0-12 (24" scale) U-tube manometer
(2) 6-0-6 (12" scale) U-tube manometer
Screwdrivers (assorted sizes and shapes)
(1) Crescent wrench (8" or 10")
(1) Multi-meter
(1) Flue gas analyzer
(Metric Allen wrenches will be required for servicing
the gas valve, but not during start-up)
Preparation
Check Power Supply
With multi-meter at incoming power, check voltage
NOTE: Digital manometers are not recommended.
47

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Xtherm 2505Xtherm 3005Xtherm 3505Xtherm 4005

Table of Contents