Setting Up Wall-Mount Unit for
Operation
The TEC-EYE
hand-held diagnostic tool, shipped
TM
with the LV1000 controller, is needed to complete the
installation of the wall-mount unit. Refer to page 26
for information on connecting and using the TEC-EYE
before proceeding with unit set up.

Setpoints

If at any time the unit(s) loses communication with the
LV1000 controller, the unit(s) will go into stand alone
mode. Local cooling and heating setpoints only apply to
stand alone mode.
The LV1000 setpoints will determine the cooling and
heating setpoints when communicating with the wall
units. The unit cooling and heating setpoints will
determine the cooling and heating setpoints when in
stand alone mode.
To verify or change the wall-mount unit cooling and
heating setpoints (local):
1. Connect the TEC-EYE
control board located in the unit (as shown in
Figure 2.2 on page 26).
2. From the Status screen, press UP or DOWN key
until Quick Menu displays Setpoints icon (see
Figure 2.3 on page 27 ). Press ENTER key.
3. Press ENTER key to scroll to the selected choice
(see Figure 1.14).
4. Press UP or DOWN key on desired value until value
displays correctly.
5. Press ENTER key to submit value and move to next
parameter.
6. Press ESCAPE key until Main Menu screen is
displayed.
FIGURE 1.14
Cool and Heat Setpoints

Executing a Run Test

Execute a run test on each unit to verify the equipment
is functioning correctly. The run test parameters are not
adjustable.

COMPLETING WALL-MOUNT SET UP

diagnostic tool to the
TM
1. Press MENU key to access the Main Menu screen.
2. Press UP or DOWN keys and ENTER key to enter
USER password 2000.
3. Press UP or DOWN keys to scroll to Sys Config;
press ENTER key.
TM
4. Press UP key to scroll to Run Test (A10) screen.
5. Press ENTER key to scroll to Run Test Enable
parameter (see Figure 1.15).
6. Press UP or DOWN key to change value to ON. The
run test will begin.
Parameter Description
Damper Test Volts: This is the control voltage applied to
the actuator during opening sequence for damper.
Damper Time: This is the time (in seconds) allowed for
both the opening sequence and closing sequence.
Heat/Cool Time: This is the time (in seconds) allowed
for cooling sequence and heating sequence.
Run Test Approximate Timings (in Minutes)
0:00
• Blower starts.
• Damper begins to open to damper test volts
parameter. To verify damper operation, open
unit side door. Inspect upper and lower
blades.
2:30
• Damper begins to close to 0 volts.
5:00
• Compressor turns on. Condenser fan
may also turn on depending on ambient
conditions.
6:00
• Compressor turns off. Condenser fan turns
off (if applicable).
• Heat turns on.
7:00
• Heat turns off.
8:00
• Blower turns off.
FIGURE 1.15