2. Installation

Step
Installing the Loader
Mounting the vacuum
hoses (Grey GTG Hose)
Connecting the material
hose (White PVC Hose)
Connecting the signal
cords
[WO-4841;JL4-V・VC-3~6-14]
Install the equipment as shown in 2. Flow diagrams in Chapter 1.
Task
Install the loader near each collection hopper (within the reach of the
5m-long air suction hose) in the vicinity of respective collectors.
* When the installing location is
determined, be sure to apply the caster
brakes (4 locations) to secure. As shown
in the diagram, the brake is applied by
stepping down on the ON side.
Connect the vacuum hoses to the suction ports of each collection
hopper and the 3 ~ 6 way selector valve of the loader.
* Be sure to secure with a hose clamp.
* A direction label (No1.~ No.6) is attached to respective hose
openings on the selector valves. Please make sure to connect to
each proper valve.
Securely tighten the hose clamps to avoid leaks at the intake ports of
Connect the material hose to the material port of each collection
hopper.
Install the suction nozzle to the end (conveying source side) of the
conveying hose.
* Firmly secure with a hose clamp.
Connect the signal cords (with connector) of the loader to the signal
cord, or socket, of the collection hopper. Make sure each cable
matches the corresponding hose direction!
- 14 -
Description
For 3 way
(3 ~ 6 way selector valve viewed from above)
NOTE
the material & vacuum hoses.
Chapter 3 Installation
For 4 – 6 way

Advertisement

Table of Contents
loading