installation
|
16

GAS CONNECTION

GAS CONNECTION
WARNING:
Only persons licensed to work
with gas piping may make the
necessary gas connections to
this appliance.
1) If the appliance is to be installed into an existing
chimney system, thoroughly clean the masonry
or factory built fireplace.
2) The appliance is provided with an opening on
the left hand side of the control compartment.
A 3/8" NPT gas supply pipe must be brought
near this inlet hole.
3) Locate the center point where the vent will pass
through the chimney above the appliance. Move
the appliance into the exact location where it is
to be installed. Ensure that the Insert is level.
THE APPLIANCE MUST NOT BE
CONNECTED TO A CHIMNEY FLUE
SERVING A SEPARATE SOLID FUEL
BURNING APPLIANCE.

VENTING

This appliance is designed to be attached to two
3" (76mm) co-linear aluminium flex running the full
length of the chimney. The flue length must be a
minimum length of 8 ' (2.44m) and a maximum
of 35' (10.7m). See chart above for minimum
distances from roof. Periodically check that the
vent is unrestricted.
Masonry chimneys may take various contours
which the flexible liner will accommodate. However,
keep the flexible liner as straight as possible,
avoid unnecessary bending.
Part #
Description
948-305
3" Flex - 35 ft.
946-529
Regency Co-linear DV Vertical
Termination Cap
Alternate Approved Caps
46dva-VC
Vertical Termination Cap
46dva-VCH High Wind Cap
46dva-GK
3" Co-linear Adaptor with flashing
16 |
E33-10 FPI Direct Vent Gas Insert
In areas of consistently high winds, we recommend
using the Simpson Dura-Vent System (46dva-GK
adapter and 46dva-VCH high-wind cap).
The Air Intake pipe must be attached to the inlet air
collar of the termination cap.
FLUE LINER
INSTALLATION
1) Cut the flex liner as required.
2) Mark the end of one liner with an "E" to
indicate Exhaust.
3) Connect the other end of the above liner to
the exhaust side of the termination adaptor,
seal connection with high temperature silicone.
Secure with 3 screws.
4) Connect the 2nd liner to the inlet side of the
adaptor, seal connection with high temperature
silicone. Secure with 3 screws.
5) Install flashing.
6) Insert both liners into chimney, passing through
the damper opening.
7) Install termination cap.
8) Remove vent connector plate by removing
screw located on top/front of appliance.
9) Connect the marked end of the liner to the
exhaust collar of the vent connector plate
marked with an "E", seal connection with high
temperature silicone. Secure with 3 screws.
10) Connect the 2nd liner to the intake collar, seal
connection with high temperature silicone.
11) Align vent connector plate with guides on unit.
12) Slide unit into masonry opening, while ensuring
that the slot at the rear of the connector plate
mates up with the hold down plate on the unit.
13) Secure with Screw–removed from Step 8.
Secure with 3 screws.
NOTE:
1) Final gas connection should be made after
unit is in place to avoid damage to line when
pushing the unit into position.
2) Mill-pac may be used instead of high tempture
silicone and screws may be used instead of
gear clamps at connections of liner to inlet and
vent collars.