Description Of Heating Engineer Settings; Service Values; Output Test - Siemens RVA63.242 User Manual

Boiler and heating circuit controllers
Table of Contents

Advertisement

Benefits
Description
Setting
Effect
Test sequence
Note
72/218
Siemens Building Technologies
Landis & Staefa Division
4
Description of heating engineer
settings

Service values

4.1 Output test

Connections can be checked prior to commissioning.
Faults can be pinpointed faster.
Also termed relay test, which is used to check the wiring and the configuration.
Setting range
0...9
The output test will automatically become available on this line.
With each test step, the respective output will be activated so that it can be checked.
The test sequence is arranged in the form of a ring counter. This means it can be run
through either forward or backward by pressing the + / - buttons.
For more information, refer to "commissioning" in Index.
Test step 0
All outputs are switched according to normal control operation
Test step 1
All outputs are deactivated
Test step 2
Burner stage 1 (K4) is activated
Test step 3
Burner stages 1 and 2 (K4 + K5) are activated
Test step 4
D.h.w. charging pump / diverting valve (Q3 / Y3) is activated
Test step 5
Mixing heating circuit / boiler pump (Q2) is activated
Test step 6
Mixing valve OPEN (Y1) is activated
Test step 7
Mixing valve CLOSED (Y2) is activated
Test step 8
Multifunctional output (K6) is activated
Test step 9
Multifunctional output (K7) is activated
Basic Documentation RVA63.242, RVA53.242

Description of heating engineer settings

Unit
Increment
Factory setting
0
CE1P2373E
26.03.2001

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rva53.242

Table of Contents