Placing the heating system in operation

11.4 Conducting final commissioning for G124X SP boiler

The final commissioning for the G124X II boiler is
described in (
Chapter 11.3, page 32).
The following start-up procedures must be carried out
regardless of the control type.
35. Look at the igniter through the sight glass in the
burner housing.
36. Turn gas valve ON/OFF switch counterclockwise to
PILOT position.
37. Press reset button in completely and hold.
38. Ignite the pilot burner with the supplied match holder
and a burning match through the sight glass in the
burner housing.
39. When the pilot burner is burning, continue to hold
the red reset button for about a minute.
40. Release red reset button. The red reset button must
pop up and the pilot burner must continue burning. If
the pilot burner goes out, switch ON/OFF switch on
gas valve clockwise to OFF and repeat steps 1
and 2 (regardless of the control).
Caution:
With aquastat control continue with steps 3 and 4,
with the Logamatic 2107 continue with steps 5
and 6.
Then repeat steps 35 to 39 regardless of the control
in use.
36
Installation and maintenance instructions Logano G124X II/SP special gas-fired boiler • Issue 04/2005
1
Fig. 34 G124X SP boiler
1 Sight glass
3
2
1
Fig. 35 G124X SP gas valve
1 Safety screw for pilot burner pressure setting
2 ON/OFF button (at ON position)
3 Reset button
4 Screw plug for gas supply pressure measuring port
5 Safety screw for manifold pressure setting
6 Screw plug for manifold measuring port