FINISHING COMMISSIONING -
APPLIANCE
1
Release support lugs (H) to pivot the
control box (A) down and into the boiler.
Secure with screws (B).
2 Locate top edge of panel (C) onto the top
supporting ledge (D) on the boiler.
Locate the ball stud connections (E) at the
base of the front panel (C) and push
towards the boiler to secure.
3 Locate the top panel (F) onto the ball stud
connections (G) and press down to secure.
G
Always apply pressure at the edges of
the boiler panels when securing to avoid
accidental damage.
H
E
Handover:
Complete the Guarantee Registration Card,
Combustion Record (at the rear of this
manual) and CD11 or an equivalent
commissioning form.
K
Set up the controls and show the user how
to operate all the controls shown in the User
Guide and all system controls.
Where applicable, instruct the customer how
to repressurise the system.
If the appliance is unused and exposed to
freezing conditions, shut off all the mains
supplies and drain the system and boiler.
NOTE: Release drain point (K) to drain the
secondary heat exchanger.
FINISHING COMMISSIONING -
37
APPLIANCE

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Greenstar heatslave 25/32Greenstar heatslave 18/25

Table of Contents