8 716 106 252f
30/3/10
12:56
A
B
1
4
2
Plan sectional view
12/18kW & 18/25kW
FRONT
INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER GREENSTAR HEATSLAVE 12/18-18/25-25/32
8 716 106 252f (03/2010)
Page 41
3
Plan sectional view
25/32kW
C
D
FRONT
INSPECTION AND SERVICE
Combustion chamber:
Release the M10 retaining nuts and washers
(B) and remove combustion chamber access
door (A).
Check the fibreglass rope seal on the
combustion chamber access door (A) and
replace if necessary.
Remove and check the baffle retainer (D).
Remove the baffles (C), clean and check the
condition of the baffles and the acoustic
E
insulation. Replace any baffles or insulation
pads considered to be badly corroded/degraded.
Thoroughly clean all of the heat exchanger
surfaces using a suitable brush and clear all
loose debris from the combustion chamber.
Check the condition of the combustion
chamber access door insulation. If the
insulation is damaged the door assembly
must be replaced.
Refit the items in reverse order ensure the
baffles (C) and baffle retainers (D) are
correctly fitted for the boiler output as shown
in the plan view opposite.
Refit combustion chamber door (A).
IMPORTANT: Secure with nuts and
washers (B) and tighten, using the
sequence shown in figure, until the
chamber door is firmly secured, do not
over tighten the nuts.
Fire valve:
Check that the oil supply pipe has a fire valve
fitted externally to the building with the fire
valve sensor located within the
appliance case. A fire valve sensor clip (E) is
provided for this purpose.
C
D
INSPECTION AND SERVICE
41

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Greenstar heatslave 25/32Greenstar heatslave 18/25

Table of Contents