Water Circulation (C.h.) - Biasi GARDA HE SYSTEM M96.28SR/P User Manual And Installation Instructions

Wall hung, fan flue, room sealed, high efficiency gas boiler
Hide thumbs Also See for GARDA HE SYSTEM M96.28SR/P:
Table of Contents

Advertisement

General requirements
--- the drainpipe should be adequately fixed to
pevent pipe sagging.
If a part of the drainpipe runs externally this part
should be kept as short as possible and protected
to reduce the risk of freezing.
Fig. 5.2
5.8

Water circulation (c.h.)

Detailed recommendations are given in BS 6798
and BS 5449; the following notes are given for
general guidance.
For Ireland (IE), refer to I.S.813.2002.
Pipework
Copper tubing to BS EN 1057 is recommended for
water pipes. Jointing should be either with capil-
lary soldered or with compression fittings.
Where possible pipes should have a gradient to
ensure air is carried naturally to air release points
and water flows naturally to drain taps.
The appliance has a built--- in automatic air release
valve, it should be ensured as far as possible that
the appliance heat exchanger is not a natural col-
lecting point for air.
Except where providing useful heat, pipes should
be insulated to prevent heat loss and to avoid
freezing.
Particular attention should be paid to pipes pas-
sing through ventilated spaces in roofs and under
floors.
By---pass
The appliance includes an automatic by--- pass
valve which protects the main heat exchanger in
case of reduced or interrupted water circulation
through the heating system due to the closing of
thermostatic valves or cock--- type valves within the
system.
The by--- pass is calibrated to assure a minimum
flow of 500--- 600 lts/hr through the main heat ex-
changer.
18
Condensate drain
If you are installing a system that includes thermo-
static radiator valves (TRV) and/or small bore
(8--- 10 mm) it may be necessary to fit an external
by--- pass to facilitate correct operation of the
boiler.
Air release points
These must be fitted at all high points where air will
natural collect and must be sited to facilitate com-
plete filling of the system.
Expansion vessel
The appliance has an integral sealed expansion
vessel to accommodate the increase of water vol-
ume when the system is heated.
Refer to Tab. 4.1 on page 11 for its technical data.
If the heating circuit has an unusually high water
content, calculate the total expansion and add an
additional sealed expansion vessel with adequate
capacity.
Mains water feed: central heating
There must be no direct connection to the mains
water supply even through a non return valve,
without the approval of the Local Water Authority.
Filling
A method for initially filling the system and replac-
ing water lost during servicing must be provided
and it must comply with local water authority regu-
lations.
The correct method is shown in Fig. 5.3.
The temporary connection must be removed
immediately after filling.
Supply pipe
(cold water inlet)
C.h. return pipe
Fig. 5.3
The installer should ensure that no leaks exist
either inside the boiler or on the system as fre-
quent filling of the system could cause premature
scaling of the heat exchanger.
For Ireland (IE), refer to I.S.813.2002.
rev 17 09 93
Control valve
Double check valve
Temporary
connection
Control valve