Installation Standard Work Checklist

This standard work checklist is to be used by the installer in conjunction with, not instead of, the instructions contained in this
installation manual.
Customer:
Lot/Address:
Model (circle one): PRIMO48
WARNING! Risk of Fire or Explosion! Failure to install appliance according to these instructions can
lead to a re or explosion.
Appliance Install Sections 3 , 6 and 11
Veri ed that the chase is insulated and sealed. (Pg. 17)
Veri ed clearances to combustibles. (Pg. 12)
Fireplace is leveled and secured. (Pg. 27)
Barrier glass installed correctly. "THIS SIDE OUT" is readable. (Section 11)
Venting/Chimney/PowerFlow™ Heat Management Sections 4,5 and 7
Venting con guration complies to vent diagrams. (Section 4)
Venting installed, locked, secured in place and sealed with correct clearance.
Firestops installed. (Section 5)
Attic insulation shield installed. (Section 5)
Exterior wall/Roof ashing installed and sealed. (Section 7)
Terminations installed and sealed. (Section 7)
PVI-SLP or PVLP-SLP power vent installed with correct baf e setting.
HEAT-ZONE-PRIMO and/or HEAT-OUT-PRIMO installed and vented
properly; complies with vent run min./max. requirements in installation manual.
Electrical Section 8 (Pg 46-50)
Unswitched power (110-120 VAC) provided to the appliance.
LED switch wires properly installed.
If only HEAT-OUT-PRIMO is installed: Wall switch plate and toggle switch not installed.
Gas Section 9 (Pg 51-55)
Proper appliance for fuel type.
Was a conversion performed?
Leak check performed and inlet pressure veri ed.
Veri ed proper air shutter setting for installation type.
Verify that the gas access plate remains installed. (Pg 54)
Finishing Section 10 (Pg 56-75)
1/2 inch sheetrock used as recommended.
Veri ed all clearances meet installation manual requirements.
Mantels and wall projections comply with installation manual requirements.
Granite or Clean Face nishing complete and complies with clearance
requirements in installation manual.
Barrier glass properly installed.
Appliance Setup Section 11 (Pg 76-78)
All packaging and protective materials removed (inside & outside of appliance).
Glass or granite panels and media installed correctly.
Firebox glass assembly installed and secured.
Accessories installed properly.
Manual bag and all of its contents are removed from inside/under
the appliance and given to party responsible for use and operation.
Started appliance and veri ed no gas leaks exist.
Multicolored LED lights work in all switched positions.
Hearth & Home Technologies recommends the following:
• Photographing the installation and copying this checklist for your le.
• That this checklist remain visible at all times on the appliance until the installation is complete.
Comments: Further description of the issues, who is responsible (Installer/ Builder/ Other Trades, etc) and corrective
action needed _____________________________________________________________________________________
_________________________________________________________________________________________________
Comments Communicated to party responsible ____________________ by ______________________on ___________
= Contains updated information.
Heat & Glo • PRIMO48, PRIMO48ST, PRIMO60, PRIMO60ST, PRIMO72, PRIMO72ST Installation Manual • 2310-970 Rev. L • 2/16
ATTENTION INSTALLER:
Follow this Standard Work Checklist
PRIMO60
PRIMO48ST PRIMO60ST PRIMO72ST
(Builder / Gen. Contractor/) (Installer)
Date Installed:
Location of Fireplace:
Installer:
PRIMO72
Dealer/Distributor Phone #
Serial #:
YES
IF NO, WHY?
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
___________________________
2310-972 Rev. C 2/16
(Date)
3

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Primo48Primo72Primo48stPrimo72stPrimo60st

Table of Contents