Figure 2. Recommended service clearances
24"
model B, vertical cabinet
model L, low vertical cabinet
12"
both sides
model D, horizontal cabinet
Units have either right or left hand piping. Reference piping locations by facing the front of the unit
(airflow discharges from the front). The control panel is always on the end opposite the piping.
The fan board assembly and main drain pan are easily removable for cleaning. See
p. 101

Pre-Installation Checklist

Complete the following checklist before beginning unit installation.
UNT-SVX07B-EN
12"
both sides
3"
model A, vertical concealed
model K, low vertical concealed
model H, vertical recessed
8.5"
both sides
24"
front discharge
28"
for more details on servicing.
Verify the unit size and tagging with the unit nameplate.
Make certain the floor or foundation is level, solid, and sufficient to support the unit and
accessory weights. See
"Dimensions and Weights, " p.
positioning the unit if necessary.
Allow minimum recommended clearances for routine maintenance and service. Refer to unit
submittals for dimensions.
Allow one and one half fan diameters above the unit before the discharge ductwork makes any
turns.
both sides
36"
model C, horizontal concealed
model E, horizontal recessed
Pre-Installation
8.5"
28"
14. Level or repair the floor before