Fitting The Flue System - Biasi Advance Plus 25C ERP User Manual And Installation Instructions

Wall hung, fanflue, roomsealed, high efficiency gas boiler
Hide thumbs Also See for Advance Plus 25C ERP:
Table of Contents

Advertisement

M
T
Q
U
R
Fig. 6.3
• Connect the pipe 11 (Fig. 6.4) from the
pressure relief valve to the safety dis-
charge pipework.
• Fit the condensate drain 9 (Fig. 6.4) in to
the drainage pipework.
• See also section 5.7 in this manual.
9
Fig. 6.4
• Fit the filling loop "S" to the pipes d.c.w.
inlet "T" and c.h. return "U". See also sec-
tion "Water circulation (c.h.)" pag. 41 in
this manual.
INSTALLATION
L
N
O
P
O
N
S
11
6.7

Fitting the flue system

For a correct installation of the flue pipe, re-
fer to the sheet provided together with the
pre-selected kit.
The horizontal routes of the flue pipes must
incline about 1.5 degrees (25 mm per me-
ter); therefore the terminal must be higher
than the intake at the boiler.
The single coaxial pipe with the terminal
must be fitted horizontal as the drainpipe is
already angled with the correct incline.
CORRECT system for installing the wall
flue
A+S
ASA
Fig. 6.5
A = air intake
S = flue exhaust