1-1 Refrigerant Refill Procedure
If connecting pipe of more than 5 metres is installed, additional refrigerant should be charged by extra
metre. You don't have to charge additional refrigerant up to 5 metres of connecting pipe.
1. Remove the valve stem cap and service port of 3-way
valve.
2. Connect the charging hose of low pressure side of
Manifold gauge to the packed valve having a charging
port(1/2" Packed valve) as shown at the right figure.
3. Operate the unit at the cooling mode.
4. Slowly open the valve of the low pressure side of
Manifold gauge counterclockwise until the low pressure
of manifold gauge indicates 4.8 to 5.5 kg/cm
78psi) at the high cool operation (1-unit operation) and
the standard temperature.
It is recommend that refrigerant should be slowly put in.
If the refrigerant is put in too quickly, compressor will be
damaged.
5. Stop operation of the air conditioner.
6. Disconnect the charge hose of manifold gauge.
7. Close the cap of each valve.
• Piping length and the height
AD26B1C13
AD18B1C09
Additional refrigerant charge
(R22,g)
• When length of the pipe is
over 5u by the unit, you
should charge
the refrigerant Formulas
A-UNIT : 20gx(L a -5)/m
B-UNIT : 20gx(L b -5)/m
(La:the length of A-unit's
pipe L b :the length of
(68 a
2
B-unit's pipe)
Max.piping
Pipe Size
length
LIQUID GAS
A-UNIT
1/4"
1/2"
15m(49ft 3in)
B-UNIT
1/4"
1/2"
15m(49ft 3in)
A-UNIT
1/4"
3/8"
15m(49ft 3in)
B-UNIT
1/4"
3/8"
15m(49ft 3in)
INDOOR UNIT
INDOOR
A-UNIT
INDOOR
B-UNIT
Max
height
A
B
7m(23ft)
7m(23ft)
7m(23ft)
7m(23ft)
A
B
OUTDOOR UNIT