Contents Contents ..............Safety General regulations ........Application ..........Norms and regulations ......Construction Layout of boiler .......... Operating principle ........Technical data ..............Extent of delivery Standard boiler .......... Accessories ..........Installation Boiler transport .......... Removing the casing ......... Boiler installation ........
Safety General regulations Application Norms and regulations General regulations The R600 boiler is CE approved and EN 61000-3-2 (2000) This documentation contains important applies to the following European Electromagnetic compatibility (EMC) - information, which is a base for safe standards: Part 3-2: Limits - Limits for harmonic ...
Construction Layout of boiler Operating principle Layout of boiler The R600 boiler consists of the follow- ing main components: Casing Front panel Adjustable feet Control panel (below cover) Flue gas connection Air intake connection (under casing) Gas connection Flow water connection Return water connection 10 2nd (hot) return water connection (for split system use), accessory...
complete system solution. Ask your Gas valve leakage tester (not possi- supplier for more detailed information. ble for R601); 2nd Return connection for Split System use; Controlled bypass (incl. pump) incl.
The R600 boiler will be supplied as a complete unit being fully assembled and pre-tested. The maximum width is 670mm for models R601-R603 and 770mm for models R604-R607, which makes it possible to transport all mo- dels through a normal door in one pie- ce.
Installation Removing the casing Boiler transport Remove the casing before transporting the boiler, in order to avoid damage to the casing parts during transportation. Removing the casing is done as fol- lows:...
Installation Boiler installation Boiler installation The boiler should be positioned in a frost-proof boiler room. If the boiler room is on the roof, the boiler itself may never be the highest point of the instal- lation. When positioning the boiler, please note the recommended minimum clea- rance in the picture.
Installation Connecting the boiler Connecting the boiler Hydraulic connections This chapter will explain how to make The boiler should always be connected all connections to the boiler with regard in such a way, that water flow through the boiler can be ensured at all times. ...
Page 13
Installation Connecting the boiler Gas connection (1) It’s recommended to use stainless The gas connection must be made by steel or PPS fluegas systems an authorized installer in accordance The diameter of the flue gas system with the applicable national and local must be chosen by calculation ac- standards and regulations.
Commissioning Water and hydraulic system Commissioning of the boiler should be This chapter explains the commissio- carried out by authorized personnel ning of the boiler with the standard boi- only. Failure to respect this condition ler controller. When an additional sys- makes the guarantee void.
Commissioning Gas supply Condensate connection Flue and air intake connections Gas supply Check the gas supply connection to the boiler for tightness. If any leakage is found, reseal the leakage before star- ting the boiler! Remove any air between the gas valve and the gas line.
Commissioning Prepare boiler for first startup Preparation for first startup Legend: On/off switch Open the gas supply; Return (ESC) Enable the power supply to the boiler; Room temperature control Confirmation (OK) Switch on the boiler with the on/off Manual mode switch (A);...
Page 21
Combustion check at full load for natural gas G20 / G25 Start the boiler in controller stop mode and go to 50% load. Now the boiler R601-R607 operates at 50% load. Allow the boiler 10.2 ± 0.2 2, max to stabilise the combustion for 3 minutes.
Commissioning Check functionality of safety devices Gas tightness check Boiler shut down Check functionality of safety devices Ionisation electrode (6) All safety devices have to be checked Remove electrical connection from the on good functioning. Safety devices on ionisation electrode while the boiler is a standard boiler are a water flow tem- running, the boiler will go in lockout no.
Commissioning Commissioning protocol Commissioning Protocol R600 Project Boiler type Project Serial number Address Year City Nominal load (Hi) [kW] Date Nominal output (Hi) [kW] Engineer System Water pressure [bar] Installati- Roof top Water pH Ground floor Water hardness [dºH] Basement ...
Operating instructions = confirmation = cancel, return to main Overview of main functions menu Button Action Procedure Display / Function Zone 1 and zone 2 Actuate wheel left/right Comfort setpoint with blinking temperature Set room temperature Turn wheel Blinking temperature in 0,5 °C steps from 10 to 30 °C Confirm with OK button or wait 5 sec.
Maintenance Checklist Replacing the electrodes Checklist Maintenance of the boiler should be carried out by authorized personnel The following activities must be carried only. out, see following paragraphs for an extensive description of the main activi- In order to ensure continued good and ties: safe operation of the boiler, it should be ...
Maintenance Cleaning the condensate receptacle Cleaning and refilling the syphon Inspection of combustion chamber Cleaning the condensate receptacle Disconnect the plug of the fluegas temperature sensor (1); Remove the internal fluegas pipe (2) of the boiler in order to create access to the condensate receptacle;...
Maintenance Water pressure and quality Combustion analysis Gas tightness check Check if the water pressure and quality Check the combustion at full load and Check the tightness of all sealed con- meet the requirements. Consult the minumum load, correct the settings if nections with an approved soap or chapter “commissioning: water and necessary.
Maintenance Maintenance Protocol Maintenance Protocol R600 Project Boiler type Project Serial number Address Year City Nominal load (Hi) [kW] Date Nominal output (Hi) [kW] Engineer System Water pressure [bar] Water pH Water hardness [dºH] Water chloride [mg/l] Water ∆T full load [ºC] Water ∆p [kPa]...
Lockouts In case of a lockout, a warning symbol ( ) and a flashing error code appears on the display. The cause of a fault should first be determined and eliminated before the boiler is being reset. The table below shows all possible lockouts with indication of possible cause.
Page 33
Lockouts Error Description of error code Internal error Parameterization error Unit manually locked Fan error LP error, does not close Error heating circuit flow switch LP error, does not open Alarm contact H1 or H4 active Alarm contact H2 (EM1, EM2 or EM3) or H5 active Alarm contact H6 active Alarm contact H3 or H7 active Limit thermostat heating circuit 1...
Page 34
Lockouts Error Description of error code Buffer return valve Y15 not available Puffer address sensor Primary controller / system pump address error Pressureless header address error Common flow sensor B10 not available Flow temperature 3 (heating circuit 3) supervision Limit thermostat heating circuit 3 Extension module 3 error (collective error) Buffer return valve Y15 not available Puffer address sensor...
Sensor values The diagrams show the sensor values NTC 10kΩ temperature sensor for all boiler sensors and optional sen- (flow, return, flue gas, DHW and header sensor) sors available in accessory kits. The diagrams contain average values, as all sensors are liable to tolerances. 60000 When measuring the resistance values, 55000...
Declaration of Conformity Declaration of Conformity Rendamax BV, Hamstraat 76, 6465 AG Kerkrade (NL), Declares that the product R600 Is in conformity with the following standards: EN 298 EN 656 EN 15420 EN 55014-1 / -2 EN 61000-3-2 /-3 EN 60 335-1/ -2 And in accordance with the guidelines of directives: 92 / 42 / EEC (boiler efficiency directive) 2009 / 142 / EEC (gas appliance directive)
Need help?
Do you have a question about the R601 and is the answer not in the manual?
Questions and answers