Initial Startup and the Configuration Program—The UPS ships with a default 127 VAC L-N
setting. This is also the most robust setting in that it can operate with either input phase angle (120
degrees). Perform initial system checks first. If the UPS configuration needs to be modified for
your application, then go to the next section to review use of the configuration program. Some
configuration changes require that the UPS be in the OFF mode while powered from the utility. Therefore,
the installer must confirm that the UPS input has been properly wired. After re-configuring your
UPS, the UPS may be put into service with the intended loads.
7.1

Hardwire Input Connections

WARNING
!
Miswiring power to the input terminal block (L1-L2-N-G) or connecting to single-phase
voltages (L-N-G only) may damage the UPS.
1. Verify that the input and output circuit breakers are off. (To locate the circuit breakers, see
Figure 1.)
2. During initial system checks, disconnect all loads (open load disconnects).
3. Inspect all wiring, cables and connection.
4. If external battery cabinets are used, verify that the battery interconnect cables are fully inserted
into the sockets.
5. Turn on the battery cabinet circuit breaker.
6. Place the manual bypass breaker in the BYPASS position. The slide bracket may need to be moved
out of the way to move the breaker.
7. Turn on the branch circuit disconnect to apply voltage to the input terminal block
(see 6.3.1 - Distribution Module Electrical Connections).
8. Using a voltmeter, verify the expected L1-N, L2-N and L1-L2 voltages.
a. The bypass lamp by the switch will light.
b. If the configuration program has been used to set the L-N voltage at 100, 110 or 115, then the
input phase angle is required to be 180 degrees.
c.
If the configuration program as been used to set the L-N voltage at 120 VAC, then the input
phase angle is required to be 120 or 180 degrees (leading or lagging).
9. After verifying proper input voltage to the UPS terminal block, turn off the branch circuit power,
close all access panels to the distribution box and reapply input power.
10. Close the input circuit breaker located on the rear of the UPS. The green AC Input indicator
should illuminate on the front panel.
11. Press the On button for one second. The bypass indicator will light for several seconds before the
UPS ON indicator turns on continuously. If the batteries are charged above 90% of capacity, an
automatic battery test will run for about 15 seconds.
12. Close the Output circuit breaker on the rear of the UPS. Transfer the manual bypass breaker to
the UPS position. Slide the bracket back in place and tighten the thumbscrew. The output
terminal block will be powered at this time.
13. Review all setting option provided by the configuration program. Some changes require that the
UPS be OFF. If this is the case, these should be programmed before powering the loads. The
configuration program is described in 8.0 - Configuration Program.
14. Connect all loads for normal operation.