Starting the System
1. Turn on the power of the peripheral equipment in the system.
2. Then turn on the Main Unit.
The system starts and the initial window (Tool Box, Bin Manager or Bin Window) appears on the Computer Display.
Computer Display is shown below.
Tool Box
Bin Manager
Closing the System
1. Click "Exit" on the Tool Box.
2. Click "OK".
18
Special Button
3. Turn off the power of the peripheral equipment in the
Bin Window
system and then the Main Unit.