Checking and Testing Operations
To complete the installation, perform the following checks and tests
to ensure that the air conditioner is operating correctly.
1
Review all the following elements in the installation:
Installation site strength
Piping connection tightness to detect any gas leakages
Connection wiring
Heat-resistant insulation of the piping
Drainage
Earthing wire connection
Correct operations (follow the steps below)
Room select switch in the indoor unit
ROOM NO.
A unit
B unit
2
Apply the power to the outdoor unit.
- Check the fuse (250V~, 5A) : The fuse is open when the power line
Room select switch
A/R
B/R
(L, N) is short.
C
I
OMPLETING THE
NSTALLATION
INDOOR UNIT
A/R
B/R
Room select switch(A, B unit)