C
I
OMPLETING THE
NSTALLATION
Checking and Testing Operations
INDOOR UNIT
Room select switch(A, B, C unit)
20
E-
To complete the installation, perform the following checks and tests to
ensure that the air conditioner is operating correctly.
1
Review all the following elements in the installation:
Installation site strength
Piping connection tightness to detect any gas leakages
Connection wiring
Heat-resistant insulation of the piping
Drainage
Earthing wire connection
Correct operations (follow the steps below)
Room select switch in the indoor unit
ROOM NO
A unit
A unit
B unit
C unit
2
Apply the power to the outdoor unit.
- Check the fuse (250V~, 5A) : The fuse is opened when the power line
Room select switch
1(#51)
2(#52)
ON
ON
ON
OFF
OFF
OFF
OFF
ON
(L, N) is short.