8. SETTING AIR GUIDE VANES (AIR FLOW CONTROL)

The air guide vanes
K
appliance.
This is done by carefully bending the air guide vanes
a screwdriver or a similar object.
DO NOT repeatedly adjust the air guide vanes (more than 5 times) as this may
cause the metal of the vanes to fracture or break.
CAUTION
DO NOT attempt to adjust the air flow direction while the appliance is in operation
or hot as this can result in burn injury.
The horizontal louvres (which direct vertical air flow) are fixed and cannot be
adjusted.

9. INSTALLING THE FACIA PANEL

Install the facia
by hooking the top of the facia
L
towards the appliance body (this is the same for both Glass and Metal facia models).
Secure the facia to the appliance body with two retaining screws
discharge louvre
.
N
1
A
2

10.INSTALLING THE TOP PANEL

Push the top panel
O

11.COMMISSIONING

The gas pressures of the appliance are factory pre set for
'extended flue' installations (page 20 Options
and will normally not require adjustment.
If the appliance is used with a 'direct' flue system (page 20 Option
), the gas pressures will need to be adjusted in accordance with
I
the commissioning instruction sheet located inside the appliance
(inside plastic pouch
P
After installation check operation of the appliance.
Once installed explain to the householder the functions and operation of the heater and remote
control. Remind the customer of the need for regular service and maintenance. Ensure the 'Customer
Record' on page i of this manual is filled in and that the booklet is handed to the customer.
Rinnai
HEATER INSTALLATION
allow the installer to set and adjust the horizontal air flow distribution of the
K
K
A
down into place and secure with the screws
as shown).
to the either the left or right as required with
K
to the body and rotating the bottom
1
through the front of the warm air
M
M
N
N
,
,
and
)
II
III
IV
V
25
K
O
N
provided as shown.
P
Installation Manual
in
2

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents