4.4 Water Supply

Feed and Expansion tanks to comply with static height requirements of BS6880 &
BS6644.
Cold feed and open vent pipes to comply with requirements of BS 6644.
Pressurised system to comply with BS 7074.
It is recommended that the system pipework is flushed twice before water
treatment.
In hard water areas precautions such as water treatment should be implemented to
prevent the build up of sludge and scale.
Leaks in the system pipework should be fixed to prevent dilution of water treatment.
Maximum working water pressure is 7 bar.
For minimum water pressure see Appendix 'E' - Water Data (Page 48)
Model Type
PV105he & 125he
Figure 4.4 – Water Connection Points
HAMWORTHY HEATING LTD
Flow Connection
Return Connection
Condensate Take-Off
8
PUREWELL VariHeat he
Model Type
PV65he & 85he
500001170/K

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents