Pre-Installation Tasks

3

Tools Required

3
Pre-Installation Tasks
3.1
Tools Required
 Standard screw driver set
 Set if allen key wrench
 Set of Phillips screw driver
 Measurement tape
 Cordless drill for unpacking the crate
3.2

PC Specification

 CPU Intel i5 or i7
 min. 4 GB RAM
 min. 1x 500 GB hard disk drive, 7200rpm
 1x 128 GB Solid State Drive
 min. 4x USB ports
 2x Ethernet ports
 19" TFT monitor (touch screen is recommended)
 Windows 7, 32/64 bit version
The PC needs to be equipped with a SSD
drive (min 128GB).
3.3

Additional Materials Required

For the DJet startup prepare the following items (not shipped by DI):
3x RJ45 Cat 5 Ethernet cable length: 3m, 3m, 5m
1x Ethernet Switch 10/100/1000 MB, min. 4 ports
2x shielded USB 2.0 cable, "USB-mini B" to "USB-A"
used for camera connection, minimum length is 2 metre
goes to USB Hub
2-2
DJet 300-500-700 – HW Installation Manual