Transmission Wiring Connection Procedure; Power Wiring Connection Procedure; Procedure For Wiring Inside Units - Daikin RXYQ72PYDN Installation Manual

Vrv iii system air conditioner
Hide thumbs Also See for RXYQ72PYDN:
Table of Contents

Advertisement

7-4 Transmission Wiring Connection Procedure

• Referring to figure 19 connect the transmission wiring between out-
side unit and indoor unit, outside unit and outside unit of other sys-
tem, outside unit and outside unit of same system.
(Refer to figure 19)
1. Master unit (*)
2. Sub unit (*)
3. Outside unit A
4. Outside unit B
5. Never connect the power wire.
6. To outside unit of other system
7. Use duplex wires (No polarity)
8. Indoor unit
(*) : The Outside unit that connect the transmission wiring to BS
unit is Master unit of the multi system.
And the other units are Sub unit. (In this figure, Outside unit
A is the Master unit.)
Check operation in installation work, Onsite settings and so
on are done by operating the PC-board (A1P) of Master unit.
NOTE
• Do not connect the power wiring to terminals for the transmission
wiring. Doing so would destroy the entire system.
• When connecting wires to the terminal block on the PC-board, too
much heat or tightening could damage the PC-board. Attach with care.
See the table below for the tightening torque of the transmission wiring
terminals.
Screw size
M3.5 (A1P)
• Transmission wiring (About the symbol
should be done within the following limitations.
If they are exceeded, transmission problems may occur.
Between outside unit and BS (or indoor) unit
1
Between BS unit and indoor unit
Between outside unit and outside unit of other systems
Max. wiring length
Max. total wiring length
Max. no. of branches
[Note]
No branch is allowed after branch (See figure 20)
Max. no. of outside units of other system
that can be connected
(Refer to figure 20)
1. Branch
2. Branch after branch
Between outside unit and outside unit of same system
2
Max. wiring length
• The transmission wiring inside the EL.COMPO.BOX should be
secured using the clamp (1) as shown in figure 21.
(Refer to figure 21)
1. In the EL.COMPO.BOX
2. Retain to the EL.COMPO.BOX with the accessory clamp (1).
• Outside the units, the transmission wiring must be finished simulta-
neously with the local refrigerant piping, and wound with tape (field
supply) as shown in figure 22.
(Refer to figure 22)
1. Liquid pipe
2. Gas pipe
3. Transmission wiring
4. Insulation material
5. Finishing tape
• For multi system:
1. Transmission wiring between outside units in the same piping sys-
tem must be connected to terminals Q1 and Q2 (TO MULTI UNIT).
Connecting the wires to the F1, F2 (TO OUT/D UNIT) terminals
results in system malfunction.
2. Wiring to other systems should be connected to terminals F1 and
F2 (TO OUT/D UNIT) on the PC-board of the master unit. The
outside unit that connected transmission wiring to indoor unit is
the master unit. The others are sub unit.
12
Tightening torque (ft · lbf)
0.59 ~ 0.71
~
, see figure 19)
1
2
: 3280 ft
: 6560 ft
: 16
: 10
: 100 ft

7-5 Power Wiring Connection Procedure

• Be sure to connect the power supply wiring to the power supply ter-
minal block and hold it in place using the included clamp as shown in
the figure 23.
• The L1, L2, L3 and N phases of the power wiring should be secured
separately to the hook using the included clamp (1).
• The ground wiring should be bound to the power wiring using the
included clamp (1) to prevent outside force from being applied to the
terminal area.
(Refer to figure 23)
1. Power supply (3 ~ 460V 60Hz)
2. Earth leakage circuit breaker
3. Branch switch, Overcurrent breaker
4. Ground wire
5. Attach insulation sleeves
6. Power supply terminal block
7. Ground terminal
8. Clamp (1) (accessory)
CAUTION
• Be sure to use crimp-style terminal with insulating sleeves for con-
nections. (See the figure below.)
Crimp-style terminal
• For wiring, use the designated power wire and connect firmly, then
secure to prevent outside pressure being exerted on the terminal board.
• Use an appropriate screwdriver for tightening the terminal screws. A
screwdriver with a small head will strip the head and make proper
tightening impossible.
• Over-tightening the terminal screws may break them.
See the following table for the tightening torque of the terminal screws.
Screw size
M8 Power terminal, ground terminal
• When pulling the ground wire out, wire it so that it comes through the
cut out section of the cup washer. (See the figure below.) An improper
ground connection may prevent a good ground from being achieved.
Crimp-style terminal
• When two wires are connected to a single terminal, connect them so
that the rear sides of the crimp contacts face each other. Also, make
sure the thinner wire is on top, securing the two wires simultaneously
to the resin hook using the included clamp (1).
Terminal
Crip style
block
terminal

7-6 Procedure for Wiring Inside Units

• Referring to figure 24, secure and wire the power and transmission
wiring using the included clamp (1), (2), and (3).
• Wire so that the ground wiring does not come into contact with the
compressor lead wiring.
If they touch, this may have an adverse effect on other devices.
• The transmission wiring must be at least 2 in. away from the power wiring.
• Make sure all wiring do not contact to the pipes (hatching parts in the
figure 24).
(Refer to figure 24)
1. Retain with accessory clamp (3).
2. Electric conduit
3. When routing out the power/ground wires from the left side.
Power wire
Insulating sleeve
Tightening torque (ft · lbf)
4.06 ~ 5.38
Cup washer
Cut out section
Wire : narrow
Wire : thick
Resin hook
English

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents